Scope & Deliverables:

  • Budget: $1.08 million
  • Narrow, sloping and small site
  • Removal of existing building
  • Site: 812 sqm
  • Building: 490 sqm (400 sqm ground level, 90 sqm offices)
  • Timeframe: 16 weeks

Project Execution:

  • Assisting with DA and BA processes for seamless build
  • Stabilise block with construction of retaining walls
  • Creation of a central pad for the use of hydraulic crane
  • Assist in the building design to facilitate the access and egress of the crane through the building
  • Widening of the existing road

Outcome:

  • Delivered on-time and on-budget